Project Details

  • Estimated Cost:  $70.0 million
  • School will be built on 80 acre tract at the southwest corner of New Road and Old Robinson Rd.

Schedule

  • Floor Plan:  June 2009
  • Acquisition of Property:  August 2009
  • Elevation Design:  August 2009
  • Design and Drawings:  Fall 2009
  • Permit:  January-March 2010
  • Construction:  May 2010-June 2011
  • Open for 2011-2012 school year

Videos

UHS Construction Update Video-October 12, 2009
UHS Construction Update Video-December7, 2009
UHS Construction Update Video-March 4, 2010
UHS Construction Update Video-May 10, 2010
UHS Construction Update Video-July 29, 2010
UHS Construction Update Video-October 25, 2010
UHS Construction Update Video-October 2010 Targeting Tomorrow Show
UHS Construction Update Video-January 6, 2011
UHS Construction Update Video-February 28, 2011
UHS Dedication Video-August 14, 2011

Photo Galleries

UHS Construction Photos-August 17, 2009
UHS Construction Photos-September 28, 2009
UHS Construction Photos-December 7, 2009
UHS Construction Photos-March 4, 2010
UHS Construction Photos-May 10, 2010
UHS Construction Photos-January 6, 2011
UHS Dedication Photos-August 14, 2011

Return to Bond 2008 Project Home Page