A. J. Moore Academy (now Indian Spring) Renovations

A. J. Moore Academy

AJM Academy (now Indian Spring Middle) Renovations Project Page

Project Details

  • Estimated Cost: $4.5 million
  • Two new science labs
  • Existing science labs will be upgraded to new TEA standards
  • Cafeteria expansion
  • Library expansion

Logistics

  • Renovations to be performed during Summer 2009

Schedule

  • Design and Drawings: Fall 2008
  • Permit: January-March 2009
  • Construction: May 2009-August 2009
  • Open for 2009-2010 school year

Videos

AJM Renovation Update Video-December 8, 2009
AJM Renovation Update Video-July 29, 2010

Photo Galleries

AJM Renovation Photos-August 19, 2009
AJM Renovation Photos-September 21, 2009
AJM Renovation Photos-December 8, 2009

Return to Bond 2008 Project Home Page