New Bell's Hill Elementary

New Bell's Hill Elementary Project Page

New Bell's Hill Elementary Project Page

Project Details

  • Estimated Cost: $13.3 million
  • New school built on current Bell's Hill site
  • Preserve the site of the historical marker 

Logistics

  • Students will be relocated to a temporary campus during construction

Schedule

  • Design and Drawings: Fall 2010
  • Permit: January-March 2011
  • Construction: May 2011-June 2012
  • Open for 2012-2013 school year

Videos

Bell's Hill Elementary Groundbreaking Video-June 20, 2011
Bell's Hill Elementary Construction Update Video-October 4, 2011
Bell's Hill Elementary Construction Update Video-January 27, 2012
Bell's Hill Elementary Construction Update Video-June 2012

Photo Galleries

Bell's Hill Elementary Groundbreaking Photos-June 20, 2011
Bell's Hill Elementary Construction Photos-October 4, 2011

Documents

Bell's Hill Elementary School Site Plan Adobe Reader required
Bell's Hill Elementary School Floor Plan Adobe Reader required

Return to Bond 2008 Project Home Page